1. Pre start inspection: All connection parts must be tightened; The direction of electric rotation should be correct; Flexible and reliable clutch; The pipeline connection is firm, the seal is reliable, and the bottom valve is flexible and effective.
2. Before starting the submersible mud pump, the suction pipe, bottom valve, and pump body must be filled with water, and the upper end of the pressure gauge buffer must be filled with oil.
3. Rotate by hand to make the piston reciprocate twice. Only when there is no obstruction and the circuit insulation is good, can it be started with no load. After starting, gradually increase the load after normal operation.
4. During operation, attention should be paid to the sealing condition of each sealing device, and adjustments should be made if necessary. The pull rod and auxiliary rod should be lubricated with oil regularly.
5. During operation, it is often tested that the sand content of the mud should not exceed 10%.
6. To ensure reliable splashing lubrication, the mud pump with several speeds should be operated separately in each shift for no less than 30 seconds.
7. It is strictly prohibited to change gears during operation. When changing gears, the pump should be stopped and the gear should be shifted.
Operating procedures for mud pumps
Apr 26, 2024
Leave a message